Home › Insights › Selective coordination: when a project needs a coordination study

Power & Distribution

# Selective coordination: when a project needs a coordination study

Entogo July 21, 2026

![Low-voltage switchgear lineup with overcurrent protective devices in a power distribution room](https://entogo.ca/_astro/selective-coordination-nec-requirements.ByMF2ZPM_Zx6uY9.webp)

In short

Selective coordination means the overcurrent device nearest a fault opens first, so one short circuit does not cascade into a wider outage. The NEC requires it for emergency, standby, and other critical loads, verified with a time-current-curve study.

## Why does one fault sometimes take down a whole building?

A ground fault or short circuit on a single branch circuit should, in a well-designed system, trip only the breaker feeding that branch. Too often it trips a larger device upstream instead, cutting power to loads that had nothing to do with the fault. In an office that is an annoyance. In a hospital operating suite, a data hall, or a building full of occupied elevators, an unnecessary outage is a safety and business problem.

**Selective coordination** is the design discipline that prevents this. NEC Article 100 defines it as the “localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the selection and installation of overcurrent protective devices and their ratings or settings for the full range of available overcurrents, from overload to the maximum available fault current, and for the full range of overcurrent protective device opening times associated with those overcurrents.”

The phrase that trips up many designs is *full range of available overcurrents*. It is not enough for the nearest device to open first under a modest overload. It has to open first from a light overload all the way up to the maximum bolted fault the system can deliver.

## What separates coordination from a short-circuit rating

Selective coordination is often confused with a short-circuit current rating (**SCCR**). They answer different questions. An SCCR tells you whether a piece of equipment can survive the fault current available at its terminals without being destroyed. Coordination tells you *which* device opens when that fault occurs. Equipment can be fully rated for the available fault current and still be poorly coordinated, tripping a main breaker when a downstream breaker should have cleared the fault alone.

### Overload region versus short-circuit region

Coordination is studied on **time-current curves (TCCs)** that plot how long each device takes to open at a given current, on logarithmic axes. Engineers read these curves in two zones divided roughly at 0.1 second. Above 0.1 second is the overload region, governed by long-time and short-time settings. Below it is the short-circuit region, governed by short-time and instantaneous response. Two devices can coordinate cleanly in the overload region and still overlap in the instantaneous region, where a high fault current can trip both an upstream and a downstream device at nearly the same instant. A design is only selectively coordinated when the curves stay separated across both zones.

## Where the code requires it

Selective coordination is not a blanket requirement for every circuit; it is mandated where a loss of power endangers people or critical operations. Elevators were the first, with Article 620 language dating to 1993. The 2005 NEC expanded the mandate to emergency systems, legally required standby systems, and health-care essential electrical systems, and critical operations power systems were added in 2008.

The current sections a designer should check include **NEC 700.28** for emergency systems, **701.27** for legally required standby, and **708.54** for critical operations power systems, each requiring that system overcurrent devices be “selectively coordinated with all supply-side overcurrent protective devices.” NEC 620.62 covers multiple elevators on a common feeder, and in health-care facilities NEC 517.17(G) requires the essential electrical system to be coordinated for fault durations that extend beyond 0.1 second. NEC 700.28 also specifies that the coordination be selected by a licensed professional engineer or other qualified person and documented for those who install, inspect, and maintain the system.

## What a coordination study actually involves

A study starts with a system **one-line diagram** and a short-circuit analysis. The engineer needs the utility available fault current at the service, transformer capacity and impedance, generator subtransient reactance, and conductor lengths and impedances, because the fault current, and therefore the coordination, changes at every point in the system. Each protective device is then plotted, and the design is adjusted until the downstream curve clears before the upstream curve begins to operate at every credible fault current.

Achieving that separation usually shapes the equipment selection. Adjustable electronic trip units on low-voltage power breakers, short-time-delay bands, current-limiting fuses, and fuse-to-fuse or fuse-to-breaker ratio tables are the common tools. This is why coordination is a specification decision, not just a study performed after the gear is bought. Lineups such as [low-voltage switchgear and MCCs](https://entogo.ca/products/low-voltage-switchgear-mcc), [drawout switchgear](https://entogo.ca/products/low-voltage-drawout-switchgear), and [distribution switchboards and panelboards](https://entogo.ca/products/distribution-switchboard-panelboard) differ in the trip units and interrupting devices they can carry, and those choices set the coordination that is achievable downstream.

## Where it makes sense to invest beyond the minimum

Code sets the floor, but the loads that justify coordination often extend past the strict list. [Data centers](https://entogo.ca/solutions/data-centers) treat any avoidable outage of an unrelated load as lost uptime, and many owners coordinate the full distribution tree, not only the emergency branch. Industrial plants built under an [EPC scope](https://entogo.ca/solutions/industrial-epc) apply the same logic to process loads whose unplanned shutdown is expensive to restart. For campuses and utility-interface projects, coordination is part of a broader [substation and power-distribution](https://entogo.ca/solutions/substations-power-distribution) protection scheme rather than a standalone exercise.

## What a buyer should specify

Name the applicable NEC articles for the project up front, and require a documented coordination study, stamped by a professional engineer, as a deliverable rather than an afterthought. Specify equipment that can achieve the required separation, which generally means adjustable trip units or current-limiting devices rather than fixed-trip molded-case breakers at the critical tiers. Ask that the switchgear or switchboard be furnished with the trip settings the study calls for, so the installed settings match the stamped curves. Governing standards, including NEC 700.28, 701.27, 708.54, 620.62, and 517, along with the IEEE guidance on protective-device coordination, define the target the study has to meet.

Entogo builds low-voltage switchgear, [switchboards](https://entogo.ca/products/low-voltage-switchboard), and distribution equipment designed and built to those governing NEC and IEEE requirements, with the adjustable trip units and interrupting devices a coordination study depends on, and cULus/CSA certifiable on request. Because the equipment is engineered and produced in its own factory, trip devices, ratings, and configurations can be matched to a project coordination study rather than constrained by available stock. For a coordinated distribution package, [contact the engineering team](https://entogo.ca/contact) with the project one-line and the list of applicable code articles.

- Selective coordination
- Overcurrent protection
- Switchgear
- NEC
- Power distribution

Glossary: [Selective coordination](https://entogo.ca/glossary#selective-coordination) [Low-voltage switchgear](https://entogo.ca/glossary#low-voltage-switchgear-ul-1558) [Switchboard](https://entogo.ca/glossary#switchboard-ul-891) [Panelboard](https://entogo.ca/glossary#panelboard-ul-67)

FAQ

## Common questions

- **What is selective coordination in electrical systems**: It is arranging overcurrent protective devices so that only the device closest to a fault opens, keeping the rest of the system energized. The NEC defines it across the full range of overcurrents, from overload to the maximum available fault current.
- **When does the NEC require selective coordination**: For emergency systems (700.28), legally required standby systems (701.27), critical operations power systems (708.54), elevators (620.62), and health-care essential electrical systems (517), among others.
- **Who has to perform the coordination study**: NEC 700.28 states the coordination must be selected by a licensed professional engineer or other qualified person, then documented for those who install, inspect, and maintain the system.
- **How is selective coordination verified**: Engineers overlay each device time-current curve and confirm the downstream device clears a fault before any upstream device begins to open, across both overload and short-circuit current levels.
- **Does selective coordination cost more than a standard design**: It can, because it may call for breakers with adjustable trip units, current-limiting fuses, or an added distribution tier. The payback is that a single fault no longer drops unrelated critical loads.

Keep reading

## Related insights

[![Three-phase distribution transformer and low-voltage switchgear at a North American facility substation](https://entogo.ca/_astro/choosing-a-facility-distribution-voltage.B10infhs_Z2obSGL.webp) Power & Distribution ### 208, 480, or 600 volts? Choosing a facility distribution voltage North American facilities are served at 120/208, 277/480, or 347/600 volts. A higher voltage moves the same power at lower current, cutting conductor size and losses while adding transformer and safety cost. Here is how to match the voltage to the load. View](https://entogo.ca/insights/choosing-a-facility-distribution-voltage)[![Power transformer at an electrical substation with an on-load tap changer for voltage regulation](https://entogo.ca/_astro/transformer-voltage-regulation-tap-changers.LSKEj7V-_xljGw.webp) Power & Distribution ### De-energized taps or a load tap changer? Specifying transformer voltage regulation A transformer needs voltage regulation when source voltage swings beyond about 5 percent or loads are voltage-sensitive. Fixed de-energized taps correct a standing offset; on-load tap changers hold output steady continuously. Here is how to choose and specify. View](https://entogo.ca/insights/transformer-voltage-regulation-tap-changers)[![Power transformer at an electrical substation, where nameplate percent impedance sets fault current and voltage regulation](https://entogo.ca/_astro/transformer-impedance-percent-z-selection.CNeq_Jkf_24aj2F.webp) Power & Distribution ### What transformer impedance should you specify? How %Z shapes fault current and voltage drop Transformer percent impedance (%Z) sets how much fault current the secondary can deliver and how far voltage sags under load. Lower %Z means higher available fault current and better regulation; higher %Z limits fault duty but drops more voltage. Here is how to choose it and what to specify. View](https://entogo.ca/insights/transformer-impedance-percent-z-selection)

Project inquiry

## Turn the brief into a specified system.

[Talk to engineering](https://entogo.ca/contact)

## Structured data (JSON-LD)

```json
{"@context":"https://schema.org","@type":"Article","headline":"Selective coordination: when a project needs a coordination study","description":"Selective coordination means the overcurrent device nearest a fault opens first, so one short circuit does not cascade into a wider outage. The NEC requires it for emergency, standby, and other critical loads, verified with a time-current-curve study.","image":"https://entogo.ca/_astro/selective-coordination-nec-requirements.ByMF2ZPM.jpg","author":{"@id":"https://entogo.ca/#organization"},"publisher":{"@id":"https://entogo.ca/#organization"},"mainEntityOfPage":"https://entogo.ca/insights/selective-coordination-nec-requirements/","inLanguage":"en","datePublished":"2026-07-21T00:00:00.000Z","dateModified":"2026-07-21T00:00:00.000Z","keywords":"Selective coordination, Overcurrent protection, Switchgear, NEC, Power distribution","about":[{"@id":"https://entogo.ca/glossary/#selective-coordination"},{"@id":"https://entogo.ca/glossary/#low-voltage-switchgear-ul-1558"},{"@id":"https://entogo.ca/glossary/#switchboard-ul-891"},{"@id":"https://entogo.ca/glossary/#panelboard-ul-67"}]}
```

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https://entogo.ca/"},{"@type":"ListItem","position":2,"name":"Insights","item":"https://entogo.ca/insights/"},{"@type":"ListItem","position":3,"name":"Selective coordination: when a project needs a coordination study"}]}
```

```json
{"@context":"https://schema.org","@type":"FAQPage","mainEntity":[{"@type":"Question","name":"What is selective coordination in electrical systems","acceptedAnswer":{"@type":"Answer","text":"It is arranging overcurrent protective devices so that only the device closest to a fault opens, keeping the rest of the system energized. The NEC defines it across the full range of overcurrents, from overload to the maximum available fault current."}},{"@type":"Question","name":"When does the NEC require selective coordination","acceptedAnswer":{"@type":"Answer","text":"For emergency systems (700.28), legally required standby systems (701.27), critical operations power systems (708.54), elevators (620.62), and health-care essential electrical systems (517), among others."}},{"@type":"Question","name":"Who has to perform the coordination study","acceptedAnswer":{"@type":"Answer","text":"NEC 700.28 states the coordination must be selected by a licensed professional engineer or other qualified person, then documented for those who install, inspect, and maintain the system."}},{"@type":"Question","name":"How is selective coordination verified","acceptedAnswer":{"@type":"Answer","text":"Engineers overlay each device time-current curve and confirm the downstream device clears a fault before any upstream device begins to open, across both overload and short-circuit current levels."}},{"@type":"Question","name":"Does selective coordination cost more than a standard design","acceptedAnswer":{"@type":"Answer","text":"It can, because it may call for breakers with adjustable trip units, current-limiting fuses, or an added distribution tier. The payback is that a single fault no longer drops unrelated critical loads."}}]}
```

_Markdown twin of https://entogo.ca/insights/selective-coordination-nec-requirements/ — generated at build time from the same content as the HTML page. Company facts, catalogue index and contact: https://entogo.ca/llms.txt_