Start from the furnace operating cycle
Melting and holding stages impose different currents and durations. Specify the entire cycle, including interruptions and short-time peaks, before agreeing continuous and cyclic loading. A single maximum-MVA figure is insufficient.
Secondary terminals, flexible connections and any reactor must be coordinated with the furnace supplier. The required voltage steps and tap-changing duty follow the metallurgical process, not a generic distribution-transformer schedule.