Solutions

Power Equipment for AI Data Centers

Transformers, substations and switchgear for hyperscale and AI workloads — built to a 12-week standard lead time, not a multi-year wait.

Hyperscale AI data-center server-rack hall with structured cabling and aisle containment — the buyer environment Entogo powers with transformers, prefabricated substations, switchgear and battery storage

Entogo is a Canada-based power-equipment manufacturer that supplies the transformers, prefabricated substations, medium- and low-voltage switchgear and battery energy storage behind AI and hyperscale data centers across North America. The difference that matters to a data-center schedule is delivery: Entogo builds European-standard equipment to an average 12-week lead time, where the merchant transformer market now quotes one to four years.

Why is data-center power suddenly so hard to procure?

For two decades, securing transformers and switchgear for a data center was a solved problem. It no longer is. Three forces have collided at once.

First, demand has exploded. The U.S. Department of Energy and grid operators have flagged that data-center electricity demand is climbing steeply as AI training and inference workloads scale — a single AI campus can now request hundreds of megawatts, comparable to a small city. Every one of those megawatts needs transformation and distribution equipment.

Second, the supply of grain-oriented electrical steel (GOES) — the core material in every power transformer — is concentrated in a handful of mills. Industry analysts including Wood Mackenzie have documented how this single-point dependency, combined with raw-material price inflation, has stretched transformer lead times from months into years.

Third, the existing fleet is aging. Much of North America’s installed transformer base is decades old, and a replacement wave is competing for the same constrained manufacturing capacity as new data-center build-out. The result is a procurement queue where a hyperscaler and a utility replacing a 40-year-old unit are bidding for the same slot.

How does Entogo deliver in 12 weeks when the industry quotes years?

The one-to-four-year figure describes the merchant queue, not the time it physically takes to build a transformer. Entogo is not standing in that queue. It operates its own source factory with a complete, vertically integrated supply chain and keeps standard IEC/CE designs in series production — so an order enters Entogo’s own build schedule rather than the merchant allocation queue, and European-standard catalogue equipment ships in an average of 12 weeks. Only the most demanding case — a product that requires new UL or other North-American certification before it can energise — extends that timeline, and even then Entogo guarantees delivery within 36 weeks.

Against an industry baseline of one to four years, that is the difference between a data center that energises on schedule and one that sits finished but dark, waiting on a transformer.

What equipment does an AI data center actually need?

A data-center power chain is a sequence of well-defined building blocks, and Entogo manufactures across the whole sequence:

  • Power and distribution transformers step the incoming utility supply down to medium and low voltage. AI and HPC halls run at far higher power density than conventional IT — several times the load per rack — so transformers are sized for high, sustained partial-load efficiency, not occasional peaks.
  • Prefabricated substations package the transformer, MV switchgear and LV distribution into a factory-built, factory-tested unit that drops onto a prepared pad. This pulls substation construction off the site critical path, turning months of field work into days of installation.
  • Medium- and low-voltage switchgear forms the distribution backbone, with the redundancy and selectivity a Tier III or Tier IV topology demands so a single fault never takes the hall offline.
  • Battery energy storage handles peak shaving, demand-charge management and bridging to generator backup as loads swing with AI training cycles.

Why do harmonics and partial-load efficiency matter here?

Data-center loads are not ordinary. UPS rectifiers and server power supplies are non-linear loads that inject harmonic currents back into the system. Feed those harmonics into a standard transformer and it overheats, derates, and ages prematurely — you lose the very capacity you paid for.

Transformers serving these loads must be specified with the harmonic profile in mind, and the distribution system designed in line with IEEE 519, the industry standard for harmonic control. Equally, because a data center runs flat-out 24/7 but rarely at nameplate peak, equipment should be optimized for partial-load efficiency — the operating point where it actually spends its life. Entogo specifies transformer rating, vector group and impedance against the project’s one-line diagram and measured or modelled harmonic profile.

How does Entogo de-risk the data-center schedule?

The hidden risk in data-center power is not any single piece of equipment — it is mismatched lead times across separately sourced gear. A project that secures switchgear quickly but waits two years for a transformer is still two years from energising.

Entogo removes that risk by supplying the transformers, substations, switchgear and storage as a coordinated package, assembled and factory-tested as a system before shipment. One supply chain, one lead time, one tested system — delivered in weeks, not years. Equipment is built to ANSI/IEEE C57, IEEE 519 and the CSA and NEC safety codes that govern North-American installations.

For operators racing to bring AI capacity online, the constraint is rarely the servers — it is the power equipment in front of them. That is exactly the bottleneck Entogo is built to clear.

System

What the solution brings together

Power & distribution transformers

Oil-immersed and dry-type transformers that step utility supply down to the medium- and low-voltage levels a data hall needs, sized for high, sustained partial-load efficiency.

Prefabricated substations

Factory-built, factory-tested box and modular substations that drop onto a prepared pad, compressing months of on-site substation construction into days on the critical path.

Medium- & low-voltage switchgear

Metal-enclosed MV switchgear and LV withdrawable switchgear for the distribution backbone, with the redundancy and selectivity a Tier III/IV topology requires.

Battery energy storage

Containerized and integrated BESS for peak shaving, demand-charge management and bridging-to-generator backup as data-center loads spike with AI training cycles.

Harmonic-aware specification

Transformers and distribution equipment specified with the non-linear, harmonic-rich load profile of rectifier and UPS front-ends in mind, in line with IEEE 519 guidance.

Vertically integrated supply

Entogo's own source factory and controlled supply chain hold the standard lead time to roughly 12 weeks, decoupling a project's schedule from the strained merchant transformer market.

Delivery

From specification to lifecycle service

Every solution is delivered through the same engineering-to-service model that stands behind more than 1,200 delivered projects.

  1. Product selection & configuration

    Technical consultation, equipment specification, project-based product matching and optimized system configuration.

  2. Electrical design support

    Engineering assistance for power distribution, transformation, grid connection, energy storage, EV charging and microgrid applications.

  3. Manufacturing coordination

    Production planning, supplier coordination, quality supervision, factory testing and delivery management.

  4. System integration

    Integrated equipment packages assembled and validated as one system before shipment.

  5. Project delivery support

    Shipment preparation, installation coordination, commissioning support, technical documentation and after-sales service.

  6. Lifecycle service

    Ongoing technical support, maintenance coordination, spare-parts supply, product upgrades and long-term service.

Projects delivered

1,200+

Manufacturing base

20,000 m²

AC + DC production lines

10

Industry experience

15+ yrs

Products

Equipment in this solution

Entogo 10kV three-phase oil-immersed distribution transformer

Power Equipment

10kV Three-Phase Oil-Immersed Distribution Transformer

A 10kV three-phase oil-immersed distribution transformer with a fully sealed corrugated-tank design, oxygen-free copper windings and a short-circuit- resistant core for reliable utility and industrial power distribution.

View

Entogo industrial and commercial integrated liquid-cooled energy storage system cabinet

New Energy

Industrial & Commercial Liquid-Cooled Energy Storage System

An all-in-one industrial and commercial liquid-cooled energy storage system that integrates the battery cluster, BMS, EMS, PCS, liquid-cooling control and fire protection in a single cabinet for factories, commercial complexes and data centres.

View

Entogo KYN28-12 armored removable AC metal-enclosed switchgear

Distribution

KYN28-12 Armored Removable AC Metal-Enclosed Switchgear

KYN28-12 armored removable AC metal-enclosed switchgear for 12kV, 50Hz three-phase AC systems — used to receive and distribute electrical energy and to control, protect and monitor circuits.

View

Entogo 36 kV outdoor compact unit substation for renewables and industrial sites

Power Equipment

36 kV Outdoor Compact Unit Substation

A factory-assembled outdoor unit substation — incoming 34.5 / 35 kV switchgear, liquid-filled step-up or step-down transformer (1,000 – 10,000 kVA) and a low-voltage section in one weather-tight enclosure — for solar PV, wind, and industrial interconnection. Built to IEEE C37.121, ANSI C57.12.34 and IEC 62271-202.

View

Entogo GGD AC low-voltage switchgear

Distribution

GGD AC Low-Voltage Switchgear

GGD AC low-voltage switchgear for 50Hz, 380V distribution systems rated up to 3150A — used for energy conversion, distribution and control in power plants, substations and industrial and mining enterprises.

View

Entogo industrial and commercial integrated air-cooled energy storage system cabinet

New Energy

Industrial & Commercial Air-Cooled Energy Storage System

An all-in-one industrial and commercial air-cooled energy storage system that integrates the battery cluster, BMS, EMS, PCS, air-conditioning control and fire protection in a single cabinet for factories, commercial complexes and data centres.

View

FAQ

Common questions

Who makes transformers for AI data centers in North America?
Entogo is a Canada-based manufacturer that supplies transformers, prefabricated substations, switchgear and battery storage for AI and hyperscale data centers across North America. Equipment is built to ANSI/IEEE C57 and delivered in an average of 12 weeks for European-standard products, with a guaranteed worst case of 36 weeks when a product requires new UL or other North-American certification.
How can a data center avoid 2-to-4-year transformer lead times?
The multi-year lead times now common in the merchant transformer market come largely from grain-oriented electrical steel (GOES) supply constraints and a demand surge driven by data centers themselves. A manufacturer with its own source factory and a vertically integrated supply chain — such as Entogo — can hold standard delivery to roughly 12 weeks because it is not waiting in the same merchant queue.
What transformer rating does an AI data center need?
It depends on the IT load and redundancy topology, but AI and HPC halls are dense — often several times the power density of conventional data centers per the U.S. Department of Energy — so the medium-voltage transformation and distribution must be sized for high, sustained partial-load efficiency rather than occasional peaks. Entogo specifies the transformer rating, vector group and impedance against the project's one-line and harmonic profile.
Why do harmonics matter for data-center transformers?
UPS rectifiers and IT power supplies are non-linear loads that inject harmonic currents, which cause extra heating in standard transformers. Equipment serving these loads should be specified with the harmonic profile in mind and the system designed in line with IEEE 519, so the transformer is not derated or shortened in life by the very load it serves.
Can Entogo supply a complete data-center power package?
Yes. Entogo bundles the transformers, prefabricated substations, medium- and low-voltage switchgear and battery storage as a coordinated package, assembled and factory-tested before shipment, which shortens on-site commissioning and removes the risk of mismatched lead times across separately sourced equipment.

Project inquiry

Talk to engineering about power equipment for ai data centers.