Solutions

Transformer & Substation Supply for Industrial & EPC Projects

Turnkey transformers, substations and switchgear for industrial and EPC projects — engineered to your drawings and delivered in 12 weeks, not held hostage by a multi-year backlog.

Industrial refinery plant with steel piping and processing towers — the EPC project site Entogo supplies with turnkey transformers, prefabricated substations and switchgear

Entogo is a Canada-based power-equipment manufacturer supplying transformers, prefabricated substations and switchgear for industrial facilities and EPC contractors across North America. Equipment is engineered to the project’s drawings, built to ANSI/IEEE C57, and delivered in an average of 12 weeks — so the power equipment stays off the critical path instead of disappearing into a multi-year backlog.

Why is a transformer the riskiest line item on an EPC schedule?

On most industrial and EPC projects, the long-lead electrical equipment is the single biggest threat to the in-service date. The merchant transformer market now quotes one to four years, and that risk compounds in two ways.

The root cause is structural. Grain-oriented electrical steel (GOES) — the core material in every transformer — comes from a concentrated set of mills, and industry analysts including Wood Mackenzie have documented how that single-point dependency, plus raw-material inflation and a demand surge led by data centers, has stretched lead times into years. The U.S. Department of Energy has flagged transformer availability as a reliability-level concern.

The second risk is mismatched lead times. An EPC package is only as fast as its slowest item. A project that secures switchgear in months but waits two years for the transformer is still two years from energising — and the standing crews, financing and liquidated-damages exposure pile up the whole time.

How does Entogo keep power equipment off the critical path?

The multi-year backlog is the merchant queue, not the time it takes to build the equipment. Entogo is not standing in that queue. It manufactures in its own source factory with a complete, vertically integrated supply chain and keeps standard IEC/CE designs in series production — so an order enters Entogo’s own build schedule rather than the merchant allocation queue. European-standard catalogue equipment ships in an average of 12 weeks, and delivery is guaranteed within 36 weeks even in the most demanding case — a product that requires new UL or other North-American certification before energising.

For a contractor building a schedule, that turns the historically riskiest line item into a predictable one. The transformer is no longer the milestone everyone holds their breath over.

Can Entogo build to our drawings, not a fixed catalogue?

Yes — and for industrial and EPC work, that is the point. Entogo engineers transformers, substations and switchgear against the project one-line diagram, electrical schedule and site conditions, rather than forcing the design into a standard product. Vector group, impedance, rating, enclosure rating and protection coordination are all specified to the project.

Just as important, Entogo supplies the equipment as a coordinated, turnkey package — transformer, MV switchgear and LV distribution assembled and factory-tested together. Interfaces are resolved on the factory floor, not discovered during site commissioning, which shortens the on-site program and removes a class of rework that EPC schedules rarely have slack for.

What can Entogo supply for an industrial site?

  • Industrial transformers — oil-immersed units for general duty, plus dry-type and amorphous-alloy transformers for indoor, high-fire-risk or environmentally sensitive locations such as plants, mines and process facilities.
  • Prefabricated substations — modular box-type and boosting substations that move substation construction off the field critical path.
  • Medium- and low-voltage switchgear — metal-enclosed MV switchgear and LV withdrawable assemblies built to IEC 61439, with arc-flash hazard managed per IEEE 1584.
  • Battery storage and grid-connection equipment — where the site integrates on-site generation, storage or a constrained grid connection.

How is compliance and quality assured?

Entogo builds to internationally recognized standards — the ANSI/IEEE C57 family for transformers, IEC 61439 for low-voltage assemblies, and the CSA and NEC safety codes for North-American installations — under an ISO 9001 quality management system, with factory testing before shipment. Where a product requires new UL or other North-American certification, that certification step is included inside the 36-week guarantee, so compliance never becomes an open-ended schedule risk.

For EPC contractors and industrial owners, the equation is simple: the power equipment that used to define the worst case on the schedule becomes one of the most predictable parts of it. That is what a vertically integrated manufacturer delivering in weeks — not years — makes possible.

System

What the solution brings together

Engineered to your drawings

Transformers, substations and switchgear specified against the project one-line, electrical schedule and site conditions — not forced into a fixed catalogue.

Turnkey power packages

Transformer, MV switchgear and LV distribution supplied and factory-tested as a coordinated package, so interfaces are resolved before equipment reaches site.

Prefabricated substations

Modular box-type and boosting substations that move substation construction off the field critical path into a factory-built, factory-tested unit.

Industrial transformers

Oil-immersed and dry-type transformers, including amorphous-alloy and dry-type designs for indoor and high-fire-risk industrial environments.

Schedule-driven delivery

A 12-week standard lead time keeps power equipment off the project critical path, where a multi-year transformer backlog would otherwise sit.

Vertically integrated supply

Entogo's own source factory and controlled supply chain shield the project from the merchant-market lead times and GOES bottleneck that derail schedules.

Delivery

From specification to lifecycle service

Every solution is delivered through the same engineering-to-service model that stands behind more than 1,200 delivered projects.

  1. Product selection & configuration

    Technical consultation, equipment specification, project-based product matching and optimized system configuration.

  2. Electrical design support

    Engineering assistance for power distribution, transformation, grid connection, energy storage, EV charging and microgrid applications.

  3. Manufacturing coordination

    Production planning, supplier coordination, quality supervision, factory testing and delivery management.

  4. System integration

    Integrated equipment packages assembled and validated as one system before shipment.

  5. Project delivery support

    Shipment preparation, installation coordination, commissioning support, technical documentation and after-sales service.

  6. Lifecycle service

    Ongoing technical support, maintenance coordination, spare-parts supply, product upgrades and long-term service.

Projects delivered

1,200+

Manufacturing base

20,000 m²

AC + DC production lines

10

Industry experience

15+ yrs

Products

Equipment in this solution

Entogo 10kV three-phase oil-immersed distribution transformer

Power Equipment

10kV Three-Phase Oil-Immersed Distribution Transformer

A 10kV three-phase oil-immersed distribution transformer with a fully sealed corrugated-tank design, oxygen-free copper windings and a short-circuit- resistant core for reliable utility and industrial power distribution.

View

Entogo industrial and commercial integrated liquid-cooled energy storage system cabinet

New Energy

Industrial & Commercial Liquid-Cooled Energy Storage System

An all-in-one industrial and commercial liquid-cooled energy storage system that integrates the battery cluster, BMS, EMS, PCS, liquid-cooling control and fire protection in a single cabinet for factories, commercial complexes and data centres.

View

Entogo KYN28-12 armored removable AC metal-enclosed switchgear

Distribution

KYN28-12 Armored Removable AC Metal-Enclosed Switchgear

KYN28-12 armored removable AC metal-enclosed switchgear for 12kV, 50Hz three-phase AC systems — used to receive and distribute electrical energy and to control, protect and monitor circuits.

View

Entogo 36 kV outdoor compact unit substation for renewables and industrial sites

Power Equipment

36 kV Outdoor Compact Unit Substation

A factory-assembled outdoor unit substation — incoming 34.5 / 35 kV switchgear, liquid-filled step-up or step-down transformer (1,000 – 10,000 kVA) and a low-voltage section in one weather-tight enclosure — for solar PV, wind, and industrial interconnection. Built to IEEE C37.121, ANSI C57.12.34 and IEC 62271-202.

View

Entogo GGD AC low-voltage switchgear

Distribution

GGD AC Low-Voltage Switchgear

GGD AC low-voltage switchgear for 50Hz, 380V distribution systems rated up to 3150A — used for energy conversion, distribution and control in power plants, substations and industrial and mining enterprises.

View

Entogo industrial and commercial integrated air-cooled energy storage system cabinet

New Energy

Industrial & Commercial Air-Cooled Energy Storage System

An all-in-one industrial and commercial air-cooled energy storage system that integrates the battery cluster, BMS, EMS, PCS, air-conditioning control and fire protection in a single cabinet for factories, commercial complexes and data centres.

View

FAQ

Common questions

Can an EPC contractor avoid a 3-year transformer backlog?
Yes. The multi-year backlog in the merchant transformer market comes from constrained grain-oriented electrical steel (GOES) supply and surging demand. A manufacturer with its own source factory and a vertically integrated supply chain — such as Entogo — delivers European-standard equipment in an average of 12 weeks, with a 36-week guaranteed worst case when new UL or other North-American certification is required, keeping power equipment off the project critical path.
Does Entogo build transformers and switchgear to project-specific drawings?
Yes. Entogo engineers transformers, substations and switchgear against the project one-line diagram, electrical schedule and site conditions rather than forcing the design into a fixed catalogue, and supplies them as a coordinated, factory-tested package so interfaces are resolved before equipment reaches site.
Why does sourcing power equipment as one package help an EPC schedule?
The biggest schedule risk is mismatched lead times across separately procured equipment — a project that has its switchgear but waits two years for the transformer is still stalled. Supplying the transformer, switchgear and distribution as one coordinated package with a single lead time removes that risk and shortens on-site commissioning.
What industrial environments can Entogo's transformers handle?
Entogo supplies oil-immersed transformers for general industrial use and dry-type and amorphous-alloy transformers for indoor, high-fire-risk or environmentally sensitive locations such as plants, mines and process facilities. Equipment is specified to the site's loading, ambient and safety requirements and built to ANSI/IEEE C57.
Is Entogo equipment compliant for North American industrial projects?
Entogo builds to internationally recognized standards including ANSI/IEEE C57, IEC 61439 for LV assemblies and the CSA and NEC safety codes, under an ISO 9001 quality management system. Where a product requires new UL or other North-American certification, Entogo guarantees delivery within 36 weeks including that certification step.

Project inquiry

Talk to engineering about transformer & substation supply for industrial & epc projects.