Insights

Engineering notes on the energy transition

Practical, vendor-neutral explainers on power equipment, energy storage and EV charging — written by Entogo's engineering team to help utilities, developers and operators specify the right system.

Low-voltage power distribution and switchgear serving nonlinear loads governed by IEEE 519 harmonic limits

Power Quality

Harmonic distortion: what IEEE 519 requires and how to meet it

Harmonic distortion from VFDs, EV chargers, and data-center power supplies can breach IEEE 519 limits and quietly overheat neutrals, transformers, and switchgear. This guide explains the 519-2022 voltage and current limits and how to specify mitigation before it becomes a field problem.

View

Commercial battery energy storage enclosure sized for power and energy capacity

Energy Storage

How to size a battery energy storage system: power vs. energy

A battery energy storage system is sized with two independent numbers, power in megawatts and energy in megawatt-hours. Their ratio is the C-rate, which fixes how long the system runs at full output and drives cost, cooling, and site design.

View

Public EV fast-charging station with a grid connection, illustrating EV charging load management and site power planning

EV Charging

EV charging load management: sizing a site without a service upgrade

Adding EV chargers often does not require a larger electrical service. NEC 625.42 lets an energy management system cap the combined draw, so a site can be sized to the managed load instead of the full nameplate of every charger. Here is how to decide and what to specify.

View

Distribution substation and grid interconnection point for solar and battery energy storage

Renewable Grid Connection

Interconnecting solar and storage to the grid: what IEEE 1547-2018 requires

Connecting solar or battery storage to the North American grid means meeting IEEE 1547-2018 for DER behavior, using a UL 1741 SB certified inverter, and passing a utility interconnection review that scales from a fast-track screen to a full study. Here is how the pieces fit.

View

Medium-voltage arc-resistant switchgear lineup in an electrical power distribution room

Power & Distribution

Arc-resistant switchgear: when it's required and what an IEEE C37.20.7 rating means

Arc-resistant switchgear redirects the pressure and heat of an internal arcing fault away from anyone standing nearby, tested to IEEE C37.20.7. It is specified where crews work close to energized medium-voltage gear and calculated incident energy is high.

View

Pole-mounted distribution transformer governed by DOE 10 CFR 431 efficiency standards

Standards & Compliance

Transformer efficiency standards: what DOE 10 CFR 431 requires and the 2029 update

US distribution transformers must meet DOE 10 CFR 431 minimum efficiency, defined at 35 percent load for dry-type units and 50 percent for liquid-immersed. A 2024 final rule raises those floors for units built on or after April 23, 2029, and here is how the rules work and what to specify.

View

Industrial plant electrical room where power factor correction capacitor banks and switchgear manage reactive power

Power & Distribution

Power factor correction: how to clear a utility power-factor penalty

Utilities such as BC Hydro and Hydro One surcharge or re-bill on kVA when power factor falls below 90 percent. Capacitor banks raise power factor to clear the penalty, but harmonics can drive resonance, so IEEE 519 and detuned designs govern a safe install.

View

Dry-type and liquid-filled distribution transformers in an electrical power room

Power & Distribution

Dry-type vs. liquid-filled transformers - how to choose

Dry-type transformers cool with air and solid insulation while liquid-filled units use mineral or less-flammable oil. The right pick turns on installation location, fire and code rules, voltage class, efficiency, and maintenance - not on which type is generally better.

View

Commercial battery energy storage system with rooftop solar, sited under NFPA 855 fire-safety spacing rules

Energy Storage

Battery storage fire safety: what NFPA 855 and UL 9540A require

Lithium-ion battery storage in North America is governed by NFPA 855 and UL 9540A. NFPA 855 caps individual units at 20 kWh and requires three-foot separation unless UL 9540A large-scale fire-test data proves a fire will not spread, which shapes how a BESS is sited, spaced, and permitted.

View

Medium-voltage metal-clad switchgear lineup in an electrical substation and power distribution facility

Power & Distribution

Metal-clad vs. metal-enclosed switchgear: how to choose

Metal-clad switchgear uses drawout breakers and grounded metal barriers between every compartment; metal-enclosed interrupter switchgear is simpler and built for lower fault duty. Here is how North American buyers match construction class, voltage, and fault duty to the application.

View

Outdoor electrical substation with distribution transformers and overhead conductors under a clear sky in Canada

Standards & Compliance

How do transformers get approved for use in Canada?

Before a transformer can be energised in Canada, the Canadian Electrical Code requires it to be "approved" — either certified by an SCC-accredited body (a CSA, cULus or cCSAus mark) or field-evaluated to CSA SPE-1000. A US-only "UL Listed" mark is not enough. Here is how the approval system actually works.

View

Industrial plant power distribution — sizing transformer primary and secondary overcurrent protection and available fault current to NEC 450.3(B) and CEC Section 26

Power & Distribution

Sizing transformer overcurrent protection (NEC 450.3(B) & CEC 26)

How to size transformer primary and secondary overcurrent protection to NEC Table 450.3(B) and CEC Section 26 (Rule 26-254), and how to find the available fault current at the secondary for downstream AIC / SCCR — with worked US and Canada examples.

View

Entogo high- and low-voltage equipment warehouse with finished transformers and switchgear staged for distribution

Sales & Distribution

How are transformers sold? Distribution channels, reps and the 2026 demand surge

Transformers reach buyers through four channels: direct OEM sales to utilities and EPCs, independent manufacturers' reps, two-step electrical distribution, and online procurement. With a global market near US$61B and 30% power-transformer supply deficits, the sales channel and sourcing have become strategic.

View

Utility distribution substation with three-phase power transformers — selecting the correct kVA rating for a North American electrical load

Power & Distribution

How to size a transformer: a practical guide to kVA selection

How to convert a real electrical load into the right transformer kVA: the calculation, the standard ANSI/IEEE rating ladder, and the margins for continuous duty, future growth, ambient and altitude that sit between calculated load and nameplate.

View

Hyperscale data-center server hall with high-density GPU racks — Entogo power-equipment customer environment for AI training loads

AI & Data Centers

Power equipment for AI data centers: what changes when racks hit 100 kW

AI training loads have pushed rack densities past 100 kW and substation lead times past three years. This is what each layer of the data-center power chain — transformer, switchgear, energy storage — now has to deliver, and where projects actually compress the schedule.

View

Public DC fast EV charging station with transmission grid in the background — Entogo EV charging buyer-line cost reference

EV Charging

What does it actually cost to install a DC fast-charger station? A 2026 breakdown

Public ranges for "DC fast-charger installation cost" span $50,000 to over $1 million per site — too wide to be useful. The Atlas/Paren analysis of NEVI awards, NREL deployment data and Rocky Mountain Institute rate-design work converge on a tighter cost stack, and on which lines actually move.

View

Entogo pad-mounted transformer warehouse — vertically integrated transformer production buffered from the North American GOES bottleneck

Market & Supply Chain

Grain-oriented electrical steel: why one Pennsylvania mill sets the clock for the North American grid

Every power transformer needs grain-oriented electrical steel (GOES), and the DOE estimates it is roughly a quarter of large-transformer cost. North America has one domestic producer — Cleveland-Cliffs' Butler Works. This is the supply chain behind the one-to-four-year lead time.

View

Entogo transformer factory overview production floor

Market & Supply Chain

How long are transformer lead times in North America in 2026?

In 2026, transformers in North America's merchant market commonly take one to four years to deliver — driven by electrical-steel (GOES) constraints, surging data-center demand and an aging fleet. Manufacturers with their own source factory, such as Entogo at a 12-week standard lead time, sit largely outside that queue.

View

Entogo DC-coupled energy storage and charging system cabinet

Solar-Storage-Charging

Solar-storage-charging integrated systems, explained

A solar-storage-charging system pairs on-site PV, a battery and EV charging behind a single grid connection, so charging draws on stored solar instead of the service entrance — enabling fast charging at sites whose utility supply could not sustain it alone.

View

Entogo industrial and commercial integrated liquid-cooled energy storage system cabinet

Energy Storage

How behind-the-meter battery storage cuts demand charges

Demand charges are billed on a facility's highest power draw, not its total energy use. Behind-the-meter battery storage discharges during those brief peaks to cap the demand, and shifts cheap off-peak or solar energy into expensive on-peak hours — lowering both parts of a commercial electricity bill.

View

Entogo DC fast charger assembly line inside the manufacturing base

EV Charging

AC vs. DC EV charging: what North American sites need

AC charging is slower, cheaper and ideal where vehicles dwell for hours; DC fast charging delivers high power for short stops but needs far more grid capacity. Matching charger type to dwell time, site load and budget is the first decision in any EV charging project.

View

Entogo new-energy integrated PV prefabricated box substation

Power & Distribution

Prefabricated substations vs. conventional builds: when modular wins

A prefabricated substation arrives as a factory-built, factory-tested package that drops onto a prepared pad, compressing months of on-site construction into days. For space-constrained, schedule-driven or repeatable projects, the modular approach usually wins on time, quality and total cost.

View

Project inquiry

Have a project that needs engineering input?